Ethiopia
Ethiopia said Monday it had attained its second-year target for filling a mega-dam on the Blue Nile River that has stoked tensions with downstream countries Egypt and Sudan.
"The first filling already was done last year. The second one is already done today. So today or tomorrow, second filling will be announced," an official told AFP, adding there is now enough water stored to begin producing energy.
Water Minister Seleshi Bekele later confirmed the milestone, which officials had earlier predicted would come in August.
In a post on Twitter, he attributed the accelerated timeline to "extreme rainfall" in the Blue Nile basin.
The Grand Ethiopian Renaissance Dam (GERD) has been at the centre of a regional dispute ever since Ethiopia broke ground on the project in 2011.
Egypt and Sudan view the dam as a threat because of their dependence on Nile waters, while Ethiopia deems it essential for its electrification and development.
Talks held under the auspices of the African Union (AU) have failed to yield a three-way agreement on the dam's filling and operations, and Cairo and Khartoum have demanded Addis Ababa cease filling the massive reservoir until such a deal is reached.
But Ethiopian officials have argued that filling is a natural part of the dam's construction process and cannot be stopped.
Energy generation
The UN Security Council met earlier this month to discuss the project, although Ethiopia later slammed the session as an "unhelpful" distraction from the AU-led process.
Egypt claims a historic right to the Nile dating from a 1929 treaty that gave it veto power over construction projects along the river.
A 1959 treaty boosted Egypt's allocation to around 66 percent of the river's flow, with 22 percent for Sudan.
Yet Ethiopia was not party to those treaties and does not see them as valid.
In 2010 Nile basin countries, excluding Egypt and Sudan, signed another deal, the Cooperative Framework Agreement, that allows projects on the river without Cairo's agreement.
The Nile's main tributaries, the Blue Nile and White Nile, converge in Khartoum before flowing north through Egypt to drain into the Mediterranean Sea.
The process of filling the GERD's reservoir began last year, with Ethiopia announcing in July 2020 it had hit its target of 4.9 billion cubic metres.
The goal for this year's rainy season -- which had been announced before the first cycle was completed -- was to add 13.5 billion cubic metres. The reservoir's capacity is 74 billion.
With the second-year target hit, the dam can run the first two of its 13 turbines, Seleshi said Monday on Twitter.
"Intensive efforts are being made for the two turbines to generate energy," Seleshi said, adding that "early generation" could be realised "in the next few months."
'National symbol'
The $4.2-billion dam is ultimately expected to produce more than 5,000 megawatts of electricity, making it Africa's biggest hydroelectric dam and more than doubling Ethiopia's electricity output.
Ethiopia had initially planned output of around 6,500 megawatts but later reduced its target.
The first two turbines should produce 750 megawatts of electricity, increasing national output by roughly 20 percent, said Addisu Lashitew of the Brookings Institution in Washington.
It is "a significant amount" for an economy that frequently faces power shortages and is sometimes hobbled by power rationing, he said.
The milestone would also have "political implications" for a country going through "a very difficult time" in no small part because of the eight-month-old war in its northern Tigray region, Addisu said.
"The dam is seen as a national symbol, a unifying symbol. It's one of the very few things that bring together people from all walks of life in Ethiopia," he said.
"Definitely the government will try to extract some political value from the second filling."
01:00
Sudan faces severe food crisis
01:04
Urgent aid sought for Sudan's isolated regions
01:31
Egypt rallies for humanitarian support for Gaza
01:36
South Sudan's President urges focus on 2026 elections at Juba Forum
01:16
World leaders react to ceasefire in Lebanon
01:01
Chad: UN investigates sexual exploitation allegations against aid workers